GRP roofing system by JWR Roofing

Watch the slideshow below of a GRP roofing system being applied.
  • Removing the old roof
    Removing the old roof.
    Existing roof in a state of disrepair.
  • Stripping the old roof
    Removing the old roof.
    Carefully removing the old felt and board.
  • Stripping the old roof
    Removing the old roof.
    Grinding out the old felt from the wall.
  • Stripping the old roof
    Removing the old roof.
    Further preparation work.
  • Stripping the old roof
    Removing the old roof.
    Final few boards being removed.
  • Applying the new decking board
    Applying the new decking board.
    Fitting and securing of the new plywood sheeting boards.
  • Applying the new decking board
    Applying the new decking board.
    Building up the interlocking boards.
  • Applying the new decking board
    Applying the new decking board.
    Close-up of the interlocking tongue and groove boards.
  • Sealing of Joints
    Sealing of Joints.
    All joints are sealed and edging trim is being applied.
  • Application of edging trim
    Application of edging trim.
    Further edging trim applied.
  • Applying reinforced chopped strand matting
    Reinforcement matting.
    Reinforced chopped strand matting is cut to size before being applied.
  • Applying reinforced chopped strand matting
    Reinforcement matting.
    Reinforcement matting ready to be applied.
  • Application of Resin
    Application of Resin.
    Resin is applied to the boards by roller - to seal them and adhere the reinforced matting.
  • Application of Resin
    Application of Resin.
    The matting is rolled out and further resin is forced through the reinforcement matting by roller adhering it to the decking boards.
  • Application of Resin
    Application of Resin.
    Apply further resin to the reinforced matting.
  • Application of Resin
    Application of Resin.
    Once dry the resin and reinforced matting become transparent.
  • Application of Resin
    Application of Resin.
    Further resin and matting being applied to the decking boards.
  • Agitating the matting
    Agitating the matting.
    Matting must be agitated as it is being layed to remove any air bubbles.
  • Agitating the matting
    Agitating the matting.
    A more robust and harder paddle roller is used to agitate the matting as it is laid to remove any air pockets.
  • Dried resin image
    Image of dried resin.
    On close inspection you can see 4 length of dried matting and resin.
  • Dried resin image 2
    Another image of dried resin.
    Another image of the dried resin from a different angle.
  • Ready for the final top coat
    Ready for the Top Coat.
    Once completed the roof is then ready for the top coat.
  • Applying the top coat layer
    Applying the Top Coat.
    The pre-pigmented Top Coat layer is then applied by roller.
  • Applying the top coat layer
    Applying the Top Coat.
    First in one direction and then in another to ensure complete coverage.
  • Applying the top coat layer
    Applying the Top Coat.
    Further image of the top coat.
  • The finished roof
    The finished roof.
    GRP flat roofing system is now complete.
  • The finished roof
    The finished roof.
    GRP flat roofing system.
  • The finished roof
    The finished roof.
    GRP flat roofing system.

For individual images of this job click here

Call us today for your free, no obligations quotation on a new GRP flat roof.

Call us

 

Trust Mark Approved Leeds Roofers

APPROVED
TRADESMEN

 Leeds Roofers Fair Trades Members
MEMBERS
SINCE 1992

Leeds Roofers 5 StarYorkshire Roofers 5 starLeeds Roofing 5 starRoof Repairs LeedsVelux windows Leeds
5 STAR
RATING
 
GRP FLAT ROOF
GRP Flat Roofing specialists
Specialists